Week Twenty-six

Week beginning 28th November Apolgies for not posting a part two last week so here’s a wee update. We spent all Thursday making risers for the house roof ladders to sit on. We had to measure the difference between the height of the gables and the height of the trusses then subtract the depth of… Continue reading Week Twenty-six

Week Twenty-five

Week beginning 21st November. We are fast approaching our six months of having been building our house and the roof still isn’t on. Hopefully this week will see the scaffolding fully erected and the beginning of the roof works. We’re starting the day by finishing the job of adding the extra layer of batons around… Continue reading Week Twenty-five

Week Twenty-four

Week beginning 14th November 2022 We’ve checked the weather and it is going to be mixed so our plan is to fit the horizontal batons on the mega-shed while it’s dry. When it’s wet we’ll start making a door for the toilet. Right now it’s dry so we are getting on with the batoning. We… Continue reading Week Twenty-four

Week Twenty-three

Week beginning 6th November. On Saturday afternoon our car didn’t start and our neighbour Iain kindly came out in the rain to give us a jump start. After that the car seemed fine and we managed to get to Oban and back, with our shopping for the week done. We were invited to our neighbour… Continue reading Week Twenty-three

Week Twenty-two

Week beginning 31st October. We went down to Edinburgh on Friday because Pete had a dental appointment and we took Niven and Caitlin for a swim. We have been taking them to the pool regularly since they were babies and we all love being in the water. When we got back on Saturday afternoon the… Continue reading Week Twenty-two